Construction

Victory House General Partner Ltd v RGB P&C Ltd [2018] EWHC 1143 (Ch)

A ‘true value’ adjudication award can provide a genuine cross claim sufficient to defeat a winding-up petition regardless of the petition debt being a judgment debt

The case of Victory House General Partner Ltd v RGB P&C Ltd [2018] EWHC 1143 (Ch) once again demonstrates the tension in construction disputes between the nature of adjudication awards as binding, enforceable interim remedies, and the court’s insolvency jurisdiction.

The sparring parties here were the employer (“Victory”) and its building contractor (“RGB”) in the development and conversion, pursuant to a JCT Design and Build Contract 2011, of an office building.

Mid-contract, RGB served an application on Victory for an interim payment. Victory served a Payless Notice disputing the sum it was liable to pay. The dispute was referred to adjudication where the adjudicator rejected Victory’s protestations against payment and awarded RGB the full sum claimed of £682,802.88 (“the first adjudicator’s award”).

Despite further litigation by Victory, RGB obtained summary judgment in the TCC to enforce the first adjudicator’s award. Victory did not appeal the judgment, nor did it pay the judgment as ordered.

RGB subsequently served a further interim application for payment which included the sum contained in the first adjudicator’s award. Victory again disputed the application, which was referred to an adjudicator. The adjudicator valued the completed works and found that Victory had paid on account sums exceeding the true value of the completed works by £1.5 million. ‘Nil’ was therefore owing by Victory on the application.

Insolvency proceedings

RGB presented a winding up petition against Victory relying on the judgment debt (comprising the first adjudicator’s award) plus interest, namely £819,363.46.

Victory applied for notice of the petition to be restrained, along with dismissal of the petition on grounds that it had cross-claims exceeding the judgment sum. It referred to the decision of the second adjudicator that it had ‘overpaid’ by reference to the value of completed works.

Although he emphasised that the judgment was not a disputed debt and RGB were entitled to enforce it in whichever way it chose, Morgan J dismissed the petition based upon the judgment on grounds that Victory had a bona fide cross-claim in restitution on substantial grounds. If Victory were to pay the judgment, it would immediately be entitled to request repayment of the sum paid in excess of the second adjudicator’s ‘value’ award (applying Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), per Coulson J (as he then was)).

There were also no special circumstances to take the case outside of the general rule that a petition should be dismissed where there was a genuine cross claim exceeding the petition debt.

Disclaimer

The information and any commentary on the law contained on this web site is provided free of charge for information purposes only. Every reasonable effort is made to make the information and commentary accurate and up to date, but no responsibility for its accuracy and correctness, or for any consequences of relying on it, is assumed by any member of Chambers. The information and commentary does not, and is not intended to, amount to legal advice to any person on a specific case or matter. You are strongly advised to obtain specific, personal advice from a lawyer about your case or matter and not to rely on the information or comments on this site. No responsibility is accepted for the content or accuracy of linked sites.

Our Expertise